According to the Fairfax Times, work began last week in three cloverleafs along the northwest side of Route 123 between the Dulles Toll Road/Dulles Connector Road bridge and Tysons Boulevard, in preparation for the future construction of the Dulles Corridor Metrorail Project. The work was scheduled to begin on July 3 and continue through tomorrow, Tuesday, July 8, weather permitting.
"Sections of trees and vegetation will be removed within the cloverleafs at the itersection of I-495 and Route 123 in Tysons Corner. And that tree clearings will take place along Route 123 from the Dulles Airport Access Road bridge south toward Anderson Road. Work is limited to land that is needed for utility work."
Dulles Metrorail project information can be found online at www.dullesmetro.com, or by calling 703-572-0506.